Advanced Analysis
Spare Parts Calculator
How many spares to stock, using Poisson demand modelling and MTBF-based failure forecasting at the confidence level you choose.
λ = (T ÷ MTBF) × Nh
h
8,760 h is one year of continuous running.
Identical parts that draw on the same spares.
Result
Spares to stock for 95% confidence
—
- Expected failures in the period
- —
- Chance this stock is enough
- —
- Stock-out risk
- —
Working
Demand = failure rate × period × parts in service
Spares = smallest k with P(failures ≤ k) ≥ target
Assumes failures follow a Poisson process (constant failure rate) and failed parts are not repaired within the period.
Poisson demand model
When failure events are rare and independent (constant failure rate), spare parts demand follows a Poisson distribution. The key input is the expected number of failures over the planning period.
Expected failures over the period
λ = (T ÷ MTBF) × N_systemsProbability of exactly k failures
P(X = k) = e^(−λ) × λ^k ÷ k!The recommended stock is the smallest k whose cumulative probability reaches your chosen confidence level.
Choosing a confidence level
| Confidence | When to use it |
|---|---|
| 80% | Budget-conscious; acceptable for non-critical parts with short lead times |
| 90% | Standard stocking level for general industrial parts |
| 95% | Critical equipment with significant downtime costs |
| 99% | Safety-critical applications or very long lead-time parts |
Frequently asked questions
When is the Poisson model appropriate?
The Poisson model works well when failures are independent, occur at a constant rate (exponential time between failures), and the expected number per period is relatively small. For wear-out parts with increasing failure rates (Weibull β > 1), consider adjusting your MTBF to reflect the planning horizon.
How do I balance stocking cost vs. stockout risk?
Compare the cost of carrying an extra spare (unit cost × carrying rate × time) against the expected cost of a stockout (downtime cost per event × probability of need). Stock more when downtime costs are high relative to part cost.